What Wisconsin’s First 765 kV Transmission Line Means for Members
Here in Wisconsin, we’ve been lucky. Growing demand for electricity, older power plants closing and new generation coming online has further complicated an already complex electrical grid system, on fast-forward. The result is an escalated risk to reliability, and we’re closer to the sun than you may think, so to speak.
When Winter Storm Fern hit the nation in late January, it brought snow, sleet, freezing rain, and frigid temperatures, and didn’t let up for days. The historic and deadly storm stretched from Texas to Maryland. The Upper Midwest was spared the worst of it, except for the bitter cold, but we’re used to this kind of thing.
But that doesn’t mean our electricity reliability was stable—it wasn’t. The Midcontinent Independent System Operator (MISO), which manages the flow of electricity across 15 states including Wisconsin and part of Canada, was sending out critical calls to action that were passed on by Dairyland Power Cooperative and local electric cooperatives. The directive: Safely reduce your power usage or risk rolling blackouts—in the middle of the deep freeze.
Authorities say Fern caused the deaths of 174 people, mostly down south, including some who died of exposure inside their homes. More than one million people experienced power outages that lasted as long as two weeks, but the outages were mainly caused by the ice. Unlike Winter Storm Elliott (2022) and Winter Storm Uri (2021), grid operators avoided rolling blackouts, which are a controlled way to stabilize the grid when demand for power threatens to exceed the supply.
While the brunt of the big storm hit south, the threat of rolling blackouts was bearing down on Wisconsin. We are a power importer, meaning we use more power than we generate. And, during Fern, we had a problem—the calm during the storm.
“Wind was down to 5, maybe 10% of installed capacity,” explained Ben Porath, Dairyland Power Cooperative executive vice president and chief operating officer. Dairyland is a generation and transmission cooperative that provides wholesale power to most of Wisconsin’s electric co-ops.
The storm’s main wrath came over the weekend, when commercial and industrial operations are typically dark or running at lower levels, so electricity demand is down. By Monday, the storm hung on, but the wind picked up, which helped fuel the factories when we needed it the most.
“If Fern had hit on a weekday, and we had no wind, it may have been a whole different story,” said Porath.
Here in Wisconsin, we’ve been lucky.
Building the Transmission Backbone
Avoiding potentially rolling blackouts is as much about transmission as it is about generation. The grid operators, including MISO, are like the “air traffic controllers” for the grid, ensuring electricity gets to where it’s needed, when it’s needed. Even before the rapid-fire expansion of AI and data centers, MISO was rolling out ambitious plans for bigger, better, and more transmission infrastructure to accommodate the historic expansion of new energy resources over the past decade, as well as growth in electrification. Electricity now powers more of how we live—from electric vehicles to lawnmowers, heat pumps to bikes—all adding to our dependence on a strong grid and expansive transmission infrastructure.

To keep up, MISO has two packages of infrastructure projects underway that it has determined are necessary to protect reliability now and decades into the future. Tranche 1, approved in 2022, includes 18 major transmission projects for the MISO region at a cost of $10.3 billion. In December 2024, MISO approved the historic Tranche 2.1 portfolio, a massive $21.8 billion plan that includes a 3,631-mile, 765 kilovolt (kV) and 345 kV transmission “backbone” to run across the Midwest.
Next, MISO allocated the projects to select builder-owners. Because these projects are deemed necessary for the greater good of the region, the cost of building each project is spread out among all ratepayers in the multi-state area. The long-term return on investment goes to the applicant awarded the project. And Dairyland Power—a not-for-profit electric cooperative owned by the member cooperatives it serves—made the cut.
In Wisconsin, we’ve been lucky.
MariBell Transmission Project
Dairyland Power, along with project partner GridLiance Heartland, LLC, were assigned a 140-mile section of the 765 kV “backbone.” “MariBell” will run from Marion, Minn., to Bell Center, Wis., crossing through Vernon and Crawford counties in the Badger State. Relatively speaking, it’s a small piece of the much larger project, but still a very big deal to the local communities that could be impacted the most.

Knowing this, Dairyland and the MariBell team got to work almost immediately, voluntarily hosting open house events in Minnesota and Wisconsin to engage the public, seek input, and share information. The discussions covered everything from proximity to purpose, and even in this early stage, misconceptions and myths about MariBell surfaced that could use some clearing up.
#1: We have to pay for it, but it won’t benefit us.
“Absolutely not true,” said Porath, reacting to claims the line uses the Wisconsin wilderness, only to pass through.
“Think of it like the Interstate highway system. Just because I-90 doesn’t run through your local community, doesn’t mean it’s not beneficial,” Porath said. “MariBell will help all of the underlying transmission lines free up space so they can transport power to local areas with reduced congestion. Because there will be more capacity, there will be more opportunity to lower overall costs by moving the most efficient source of energy at any given time. This transmission line will redefine the energy outlook in the state in a remarkable way, for future generations.”
#2: It’s too big.

It is big, that’s true. The lattice-type structures will be 150-200 feet tall, and the cleared right-of-way areas between 200-250 feet wide. But the 765/161 kV tower will be able to carry as much power as approximately six, 345 kV lines, which means less land is impacted, overall. In addition to that, the structures will be spaced 1,200 to 1,500 feet apart, so there will be fewer of them, which means less disruption on the ground and less maintenance. One 765-kV line carries as much electrical capability as approximately six 345-kV lines, minimizing the land needed by as much as 70% to 80%.
#3: It is new, untested technology that could be detrimental to farms.
While this is the first 765 kV line in Wisconsin, there is already an existing 765 kV network in the United States.
“It runs from Illinois to the East Coast, through the Ohio River Valley and into New York. It’s been operating safely since the 70s and 80s,” Porath said. “And planning for 30 to 50 years into the future, we know it is much more efficient to have one, 765 kV line than it is to have four to six 345 kV lines”
#4: It will be harmful to the Driftless Region.
“The Driftless Region is precious, it really is,” Porath said. “We live here, too, and we know this. It is amazing. What we need to work out is how best to get the infrastructure built, while still protecting the environment. The practical reality is that the Driftless goes all the way from northern Wisconsin along the St. Croix River down to the Mississippi River and extends for many miles. So, to get power into Wisconsin, we have to cross the Driftless, but we have to do it in the most environmentally sensitive way. To us, that means using the existing utility infrastructure corridor instead of cutting a new path. We will have to expand the right-of-way, but we are working with our project team on construction vegetation management practices to protect environmentally sensitive areas. There is a way to do it right, which could include a pollinator habitat.”
The Reality of ROFR
With the rollout of $30 billion in planned transmission projects in the MISO region in recent years, many states, including Michigan and Minnesota, passed “Right of First Refusal” legislation, also known as ROFR. ROFR gives incumbent utilities priority in awarding major transmission projects in their state.
Wisconsin’s legislature failed to pass a ROFR bill. Without it, MISO’s competitive bidding process opens up access to any outside entity. In pushing for passage of ROFR in Wisconsin last year, Dairyland Power Cooperative, the Wisconsin Electric Cooperative Association, American Transmission Company (ATC), and others argued transmission projects are subject to competitive bidding and staunch oversight at every level and, without it, Wisconsin ratepayers may be required to help pay for Wisconsin projects without ever getting a dollar back in return. And that’s exactly what happened.
MISO’s Tranche 2.1 includes two Wisconsin-based projects—BECI (Bell Center-Columbia-Sugar Creek), a 200-mile, 765 kV line, and WISE (Wisconsin Southeast), a 125-mile, 345 kW line. Dairyland Power Cooperative submitted bids for both projects, but without the law granting preference to state incumbent utilities, MISO awarded BECI to Transource Energy, a partnership between Ohio-based American Electric Power and Kansas City-based Evergy, and awarded WISE to Chicago-based Viridon Midcontinent LLC, owned by New York-based Blackstone Energy Transition Partners.
Viridon’s $350 million bid was a low-ball, coming in at just over half of MISO’s estimate for the WISE project. In March, MISO reversed course and awarded the building of the substations in the WISE project to ATC, citing concerns that Viridon’s timeline was “unachievable.” Viridon retains the build rights for transmission lines and one substation.
Wisconsin lawmakers could still pass ROFR, but as Porath says, “It’s too late.” It has been more than 50 years since the last major transmission buildout and all of the projects in MISO’s Tranche 2.1 have already been awarded.
#5: Dairyland is the sole decision-maker.
Dairyland Power essentially serves as the general contractor of the project. MISO designates what projects are needed in the region to best serve the grid. Dairyland and Gridliance Heartland, who will build, own, and operate the line, will establish the need for the project and offer options for the specific route and the Public Service Commission of Wisconsin (PSCW) will decide if the project is approved and select which route the MariBell Transmission Line will take.
“This line will be built with or without Dairyland,” Porath said. “But it was really important to us to do this project because we are invested in the area. We are seeking ways to be the least impactful to local communities. We will follow existing rights-of-way as much as possible, as opposed to cutting wide swaths to previously undisturbed lands, as is sometimes the approach. The process and the people matter, and we will continue to be transparent and accessible as we work through this project together.”
#6: It will increase electric bills.
Ratepayers across the multi-state area are responsible for funding the 765 kV line, but because Dairyland was selected to build and operate the MariBell section, the income generated will pay a rate of return that will benefit Dairyland members for as long as the line is in service.
“We’re going to reduce what our members have to pay, because of the margins we’re getting for this investment,” Porath said, adding that as a not-for-profit cooperative, Dairyland’s focus is keeping costs down, not maximizing profit.
Had MISO awarded the project to an outside entity, Dairyland’s members, as part of the MISO region, would still help fund the cost of construction, but would not benefit financially via downward pressure on rates from the investment.
What’s Next
The next step in the permitting process is for the MariBell team to apply for a Certificate of Public Convenience and Necessity (CPCN) with the PSCW. During that phase, there will be additional open house events and opportunities for the public to offer feedback as part of the formal PSCW process.
The MariBell Transmission Line is planned to be in service by 2034.—Julie Lund